Question: UsingPERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and the
UsingPERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and the project variance is 4.
a) The probability that the project will be completed in 18 months=
(round your response to four decimalplaces).
b) The probability that the project will be completed in 21 months=
(round your response to four decimalplaces).
c) The probability that the project will be completed in 24 months=
(round your response to four decimalplaces).
d) The probability that the project will be completed in 26 months=
(round your response to four decimalplaces).
e) The due date that yields a95% chance of completion= ____ months (round your response to two decimalplaces).

Using PERT. Adam Munson was able to determine that the expected project completion time for the consthction of a pleasure yacht is 22 months, and the project variance is 4. a) The probability that the project will be completed in 18 months = :l (round your response to four decimal places). b) The probability that the project will be completed in 21 months = :l {round your response to four decimal places). c) The probability that the project will be completed in 24 months = 1 {round your response to four decimal places). d) The probability that the project will be completed in 26 months = :l {round your response to four decimal places). e) The due date that yields a 95% ch anoe of completion = months {round your response to two decimal places)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts