Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and
a) What is the probability that the project will be completed in 17 months?
b) What is the probability that the project will be completed in 20 months?
c) What is the probability that the project will be completed in 23 months?
d) What is the probability that the project will be completed in 25 months?
e) What is the due date that yields a 95% chance of completion?
Step by Step Solution
3.43 Rating (169 Votes )
There are 3 Steps involved in it
a Probability of completion is 17 months or less ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
286-B-M-L-O-M (2419).docx
120 KBs Word File