Question: value: 10.00 points Project management (1) Consider the following project: Activity Immeadiate Predecessors Durations (weeks) A - 5 B A 3 C A 2 D
value: 10.00 points
Project management (1)
Consider the following project:
| Activity | Immeadiate Predecessors | Durations (weeks) |
| A | - | 5 |
| B | A | 3 |
| C | A | 2 |
| D | B | 3 |
| E | C | 7 |
| F | B , C | 3 |
| G | D , E | 6 |
| H | C | 2 |
What is the project duration?
17
10
20
9
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
