Question: value: 10.00 points Project management (1) Consider the following project: Activity Immeadiate Predecessors Durations (weeks) A - 5 B A 3 C A 2 D

value: 10.00 points

Project management (1)

Consider the following project:

Activity

Immeadiate

Predecessors

Durations

(weeks)

A - 5
B A 3
C A 2
D B 3
E C 7
F B , C 3
G D , E 6
H C 2

What is the project duration?

17

10

20

9