Question: Project management (2) Consider the following project: Activity Immeadiate Predecessors Durations (weeks) A - 4 B A 3 C A 2 D B 3 E
Project management (2)
Consider the following project:
| Activity | Immeadiate Predecessors | Durations (weeks) |
| A | - | 4 |
| B | A | 3 |
| C | A | 2 |
| D | B | 3 |
| E | C | 8 |
| F | B , C | 3 |
| G | D , E | 7 |
| H | C | 2 |
Which activity is not a critical activity?
Multiple Choice
-
A
-
G
-
D
-
E