Question: Veu may need to use the appropriate technelogy to answer this question. Nueller &. Associates is a urban planning firm that is designing a new

Veu may need to use the appropriate technelogy to answer this question. Nueller \&. Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the wetk complesen dase requessed by the ewnes The Muelle projest mandger prepared the following projest network. Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activites are as follows. (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project complecion time (in weaks)? weeks