Question: Vincent Smith, a project manager, learns that a hailstorm is forecasted to interfere with project work. Weather forecast was identified during project planning as a
Vincent Smith, a project manager, learns that a hailstorm is forecasted to interfere with project work. Weather forecast was identified during project planning as a project risk. Due to the expected hailstorm, trucks may not be able to reach the factory warehouse on time and thus the material required for completing the next batch of products may not be available. He wants to identify the possible responses he could implement.
Which log or register should Vincent use to gather this information?
A
Issue log
B
Risk register
C
Riskadjusted backlog
D
Change log
A
Leadership
B
Facilitation
C
Networking
D
Active listening
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock