Question: w . Budget for the Project = $ 1 , 8 0 0 , 0 0 0 Duration of the Project = 1 2 monthsScope

w.Budget for the Project = $1,800,000Duration of the Project =12 monthsScope of the Project -10 deliverablesReported Status at end of 4 months:Budgeted Cost of Work Scheduled = BCWS = $900,000Budgeted Cost of Work Performed = BCWP = $850,000Actual Cost of Work Performed = ACWP = $875,000