Question: Wagons are assembled in a process with two resources. A worker in the first resource assembles 15 wagons per hour and a worker in the
Wagons are assembled in a process with two resources. A worker in the first resource assembles 15 wagons per hour and a worker in the second resource assembles 1.6 wagons per hour. The first resource has 1 worker and the second resource has 5 workers. Demand occurs at the rate 5.2 wagons per hour.
What is the implied utilization (%) of the second resource?
Note: Round your answer to 1 decimal place.