Question: Wast company is in interested in improving operating performance. The following data is reported. Inspection : ..............1 days Process time: ............4 days Wait time: .............10
Wast company is in interested in improving operating performance. The following data is reported.
Inspection : ..............1 days
Process time: ............4 days
Wait time: .............10 days
Queue time: ..........5 days
Move time: ..........12 days
Required:
1. Compute the delivery cycle time.
2. Compute the manufacturing cycle time.
3. Compute the manufacturing cycle efficiency.
4. If all queue time can be eliminated in production, what will be the new manufacturing cycle efficiency?
Step by Step Solution
★★★★★
3.47 Rating (157 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
The question is incomplete because it is not clear ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock