Question: We are at a complex factory which has multiple machine operations that work in a series. One of those operations includes an retro-fitting operation. If

We are at a complex factory which has multiple machine operations that work in a series. One of those operations includes an retro-fitting operation. If you were to move the retro-fitting operation from before the bottleneck to after the bottleneck, the throughput rate should

a. decrease

b. increase

c. not be affected

Step by Step Solution