Question: We consider a home security software development project. The project network and the project baseline are given below (Figures 2a and 2b). Answer the following
We consider a home security software development project. The project network and the project baseline are given below (Figures 2a and 2b). Answer the following questions:
1. Develop a project progress report at the end of each period. To do this, first complete Tables 1-3


| Tche | Pourcentage dachvement rel | VA | CR | VP | EC | EP |
| 1 | 50% |
| 4 |
|
|
|
| Totaux cumulatifs |
|
|
|
|
| |
Tableau 1 : Fin de la priode 2
| Tche | Pourcentage dachvement rel | VA | CR | VP | EC | EP |
| 1 | Termine |
| 10 |
|
|
|
| Totaux cumulatifs |
|
|
|
|
| |
Tableau 2 : Fin de la priode 4
| Tche | Pourcentage dachvement rel | VA | CR | VP | EC | EP |
| 1 | Termine |
| 10 |
|
|
|
| 2 | 25% |
| 15 |
|
|
|
| 3 | 33% |
| 12 |
|
|
|
| 4 | 0% |
| 0 |
|
|
|
| Totaux cumulatifs |
|
|
|
|
| |
Tableau 3 : Fin de la priode 6
| Tche | Pourcentage dachvement rel | VA | CR | VP | EC | EP |
| 1 | Termine |
| 10 |
|
|
|
| 2 | 30% |
| 20 |
|
|
|
| 3 | 60% |
| 25 |
|
|
|
| 4 | 0% |
| 0 |
|
|
|
| Totaux cumulatifs |
|
|
|
|
| |
2 8 4 3 5 8 4 6 4 4 4 6 8 Lgende Tche DH FH DT Dure FT Base de rfrence du projet (VP) (en $) (x 100) 10 12 14 16 18 20 22 0 2 4 6 8 N Dure D F Mar VP T ge (x 100) 4 0 8 4 8 40 10 10 10 10 6 30 10 15 5 4 20 10 10 40 20 20 8 60 20 20 10 10 4 20 10 10 8 30 20 10 VP totale par priode : 4 8 248 VP totale cum ulative : 2 8 4 3 5 8 4 6 4 4 4 6 8 Lgende Tche DH FH DT Dure FT Base de rfrence du projet (VP) (en $) (x 100) 10 12 14 16 18 20 22 0 2 4 6 8 N Dure D F Mar VP T ge (x 100) 4 0 8 4 8 40 10 10 10 10 6 30 10 15 5 4 20 10 10 40 20 20 8 60 20 20 10 10 4 20 10 10 8 30 20 10 VP totale par priode : 4 8 248 VP totale cum ulative