Question: Activity Expected time (t) Variance A 3 0.15 B 2 0.82 C 9 1.93 D 7 0.7 E 8 0.26 F 17 0.23 G 4
| Activity | Expected time (t) | Variance |
| A | 3 | 0.15 |
| B | 2 | 0.82 |
| C | 9 | 1.93 |
| D | 7 | 0.7 |
| E | 8 | 0.26 |
| F | 17 | 0.23 |
| G | 4 | 1.39 |
| H | 6 | 1.78 |
Consider the path A-C-D-G-H of the project given in the table ablve.
a)
What is the completion time for this path?
b)
What is the standard deviation of this path?
Round your answer to 4 decimal places.
c)
What is the probability the project will be completed within the due date of 28 days?
Round your answer to 4 decimal places.
d)
If you want to be 96% confident of completing the project ontime what should be the due date?
Round your answer to 1 decimal place.