Question: We discussed a Power - Interest Grid as a method of stakeholder analysis. Which of the following is false regarding a Power - Interest Grid?
We discussed a PowerInterest Grid as a method of stakeholder analysis. Which of the following is false regarding a PowerInterest Grid?
a
A stakeholder with a high level of interest would be in either the topright or bottomright quadrant when being plotted on the powerinterest grid
b
The powerinterest grid is an output from the Process Identify Stakeholders
c
A stakeholder that has a high level of power and a high level of interest should be Managed Closely
d
Power refers to the level of decision making autonomy the stakeholder possesses in relation to the project