Question: We have a flow shop problem with 2 machines and 5 jobs. The table below provides the processing time for each job on each machine.
We have a flow shop problem with machines and jobs. The table below
provides the processing time for each job on each machine.
Apply Johnson's algorithm to determine the schedule that minimizes makes
span. At each step of the method, you need to provide the set of unscheduled
jobs, the unscheduled job with the smallest processing time on machine
the unscheduled job with the smallest processing time on machine and the
job you will schedule.