Question: We have a project ( Raise _ L ) , with these activities in days: Activity A with duration 6 and no precedents. Activity B

We have a project (Raise_L), with these activities in days: Activity A with duration 6 and no precedents. Activity B with duration 10 and predecessor. A, Activity C with duration 2 and predecessor. A, Activity D with duration 6 and predecessor B, Activity E has duration 3 and predecessors B and C, Activity F has duration 1 and predecessor D, and Activity G has duration 11 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take?
22 days
33 days
34 days
39 days
4 points
QUESTION 7
From question #6, what is the ES for Node E?
15
16
17
19
4 points
QUESTION 8
From question #6, what is the EF for Node E?
19
20
21
22
4 points
QUESTION 9
From question #6, what is the LS for Node C?
17
18
20
21
4 points
QUESTION 10
From question #6, what is the EF for Node D?
20
21
22
23
4 points
QUESTION 11
From question #6, what is the slack in node D?
0 day(s)
2 day(s)
3 day(s)
5 day(s)
4 points
QUESTION 12
What is the critical path from #6?
A~B~D~F~G
A~C~E~G
A~B~E~F~G
A~B~E~G
4 points
QUESTION 13
From question #6, what is the LF for Node E?
20
22
23
24
4 points
QUESTION 14
From question #6, what is the ES for Node C?
5
6
7
8
4 points
QUESTION 15
From question #6, what is the slack in node E?
0 day(s)
1 day(s)
2 day(s)
4 day(s)
4 points
QUESTION 16
From question #6, what is the LF for Node D?
15
16
22
23

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!