Question: We have a project ( Raise _ L ) , with thes e activities in days: Activity A with duration 6 and no precedents. Activity

We have a project (Raise_L), with thes
e activities in days: Activity A with duration 6 and no precedents. Activity B with duration 10 and predecessor. A, Activity C with duration 2 and predecessor. A, Activity D with duration 6 and predecessor B, Activity E has duration 3 and predecessors B and C, Activity F has duration 1 and predecessor D, and Activity G has duration 11 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take?