Question: We have a project ( Raise _ L ) , with these activities in days: Activity A with duration 6 and no precedents. Activity B
We have a project RaiseL with these activities in days: Activity A with duration and no precedents. Activity with duration
and predecessor. A Activity C with duration and predecessor. A Activity D with duration and predecessor B Activity E has
duration and predecessors B and C Activity F has duration and predecessor D and Activity G has duration and
predecessors of and F Draw this to answer the following questions. How long is this project scheduled to take?
days
days
days
days
QUESTION
From question # what is the ES for Node E
QUESTION
From question # what is the EF for Node E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
