Question: We have a project ( RedBird ) , with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration

We have a project (RedBird), with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 1 and predecessor. A, Activity D with duration 1 and predecessor B, Activity E has duration 9 and predecessors B and C, Activity F has duration 2 and predecessor D, and Activity G has duration 17 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take?