Question: We have a project ( RedBird ) , with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration

We have a project
(
RedBird
)
,
with these activities in days: Activity A with duration
4
and no precedents. Activity B with duration
1
5
and predecessor. A
,
Activity C with duration
1
and predecessor. A
,
Activity D with duration
1
and predecessor B
,
Activity E has duration
9
and predecessors B and C
,
Activity F has duration
2
and predecessor D
,
and Activity G has duration
1
7
and predecessors of E and F
.
From question #
1
,
what is the slack in node EF
?