Question: We have a project ( RedBird ) , with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration
We have a project
RedBird
with these activities in days: Activity A with duration
and no precedents. Activity B with duration
and predecessor. A
Activity C with duration
and predecessor. A
Activity D with duration
and predecessor B
Activity E has duration
and predecessors B and C
Activity F has duration
and predecessor D
and Activity G has duration
and predecessors of E and F
From question #
what is the slack in node EF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
