Question: We have a project that needs to be crashed. There is only one critical path for the project. The tasks for this project, as
We have a project that needs to be crashed. There is only one critical path for the project. The tasks for this project, as well as a normal task time (in weeks), time when fully crashed (in weeks), cost to fully crash, and whether or not it is on the critical path, is given below. Task A B C D E F G H Normal Task Time 9 11 5 7 5 8 9 10 Time When Fully Crashed 6 10 3 4 1 6 8 9 Cost to Fully Crash $2,106.5 $1,383.4 $567 $1,228 $1,656 $2,881.5 $1,252.4 $465 Critical Path? No Yes No Yes No Yes Yes No What is the cost to crash the project for one week?
Step by Step Solution
There are 3 Steps involved in it
To determine the cost to crash the project for one week we need to calculate the cost reduction for ... View full answer