Question: We have a project that needs to be crashed. There is only one critical path for the project. The tasks for this project, as well

We have a project that needs to be crashed. There is only one critical path for the project. The tasks for this project, as well as a normal task time (in weeks), time when fully crashed (in weeks), cost to fully crash, and whether or not it is on the critical path, is given below. Task Normal Task Time Time When Fully Crashed Cost to Fully Crash Critical Path? A 11 9 $3,500 YES B 9 6 $1,900 NO C 13 10 $4,200 YES D 11 10 $2,900 NO E 12 11 $2,000 NO F 13 11 $3,100 YES G 9 7 $3,300 YES H 13 12 $1,200 NO I