Question: We have the following project, including task length (in days) and predecessors for each task: Task Completion Time Predecessors A 1 - B 4 a
We have the following project, including task length (in days) and predecessors for each task: Task Completion Time Predecessors A 1 - B 4 a C 17 a D 70 b E 10 c F 30 d G 25 e H 20 e I 25 f J 20 g,h K 25 I,k If we spend $11817 per day in labor costs, how much in dollars do we expect to spend in labor for this project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock