Question: We have the following project, including task length (in weeks) and predecessors for each task: Task Normal Task Time Predecessors A 4 - B 6
We have the following project, including task length (in weeks) and predecessors for each task:
| Task | Normal Task Time | Predecessors |
| A | 4 | - |
| B | 6 | - |
| C | 5 | - |
| D | 8 | a,b |
| E | 7 | b,c |
| F | 4 | d |
| G | 5 | e |
| H | 3 | f |
| I | 7 | f,g |
| J | 6 | g |
| K | 8 | h,I,j |
If we spend $9,823 per week in labor costs, how much in dollars do we expect to spend in labor for this project? ______________