Question: We have two projects: project A and project B. A 10% cost of capital and 10-year projects. Assume that the financial manager created three scenarios
We have two projects: project A and project B.
A 10% cost of capital and 10-year projects.
Assume that the financial manager created three scenarios for each project: pessimistic, most likely, and optimistic. The table below summarizes the cash inflows .
Calculate the range of cash inflows.
Calculate the NPV ranges.
\begin{tabular}{lcc} & Project A & Project B \\ \hline Initial investment & $10,000 & $10,000 \\ \hline & \multicolumn{2}{c}{ Annual cash inflows } \\ \hline Outcome & & \\ Pessimistic & $1,500 & $0 \\ Most likely & 2,000 & 2,000 \\ Ontimistic & 2500 & 4000 \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
