Question: We know that the CODE C is the longest in the process. Estimates of time range from an optimistic time (a) of 70 hours, a

We know that the CODE C is the longest in the

We know that the CODE C is the longest in the process. Estimates of time range from an optimistic time (a) of 70 hours, a pessimistic time (b) of 130 hours, and a most likely time (m) of 100 hours.

  1. Calculate the expected time for this step in the precedence chart;
  2. Calculate the variance and tell me what it means.
Find location; determine A Planning 20 None resource requirements B Purchasing Requisition lumber 60 and sand Planning Excavating Dig and grade site 100 Planning D Sawing Saw lumber into appropriate sizes 30 Purchasing E Placement Position lumber in correct locations 20 Sawing; Excavating F Assembly Nail lumber together 10 Placement G Infill Put sand in and under the equipment 20 Assembly H Out fill Put dirt around equipment 10 Assembly Decoration Put grass all over the garden & landscape 30 Infill; Out fill

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!