Question: We know that the CODE C is the longest in the process. Estimates of time range from an optimistic time (a) of 70 hours, a

We know that the CODE C is the longest in the process. Estimates of time range from an optimistic time (a) of 70 hours, a pessimistic time (b) of 130 hours, and a most likely time (m) of 100 hours.
- Calculate the expected time for this step in the precedence chart;
- Calculate the variance and tell me what it means.