Question: We know that there are three paths: 1. ABEG, 2. ACDEG, 3. ACDFG The duration for... 1. ABEG = 19, ACDEG = 20, ACDFG =

We know that there are three paths: 1. ABEG, 2. ACDEG, 3.We know that there are three paths:

1. ABEG, 2. ACDEG, 3. ACDFG

The duration for...

1. ABEG = 19, ACDEG = 20, ACDFG = 17

making A-C-D-E-G the critical path.

ACDFG The duration for... 1. ABEG = 19, ACDEG = 20, ACDFG

Note: Information such as crash costs of F and G were not provided for this problem in the assignment. Please solve without it.

What are the total extra cost AND the total cost of reducing the project duration to 16 days?

Consider the following construction project break-down: uppose that the goal is to reduce the project duration to 16 days. Explain, step by step, which tasks to crash, and compute esulting total cost of reducing the project duration to 16 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!