Question: We need some financial information. We are half - way complete with a six - month project. SPI = 1 . 0 7 , AC

We need some financial information. We are half-way complete with a six-month project. SPI =1.07, AC = $36,000, PV=$30,000. What is the cost variance of the project?
-$3852
-$3900
-$6000
$3900