Managers are replacing the Reorder Point (ROP) Method with Time Phased Order Points (TPOP). Using TPOP's,...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Managers are replacing the Reorder Point (ROP) Method with Time Phased Order Points (TPOP). Using TPOP's, managers are able to plan over several periods rather than period to period. Order Qty= Order Lead Time= Forecast Demand Scheduled Receipts Projected Available Inventory 120 Planned Order Receipts. Planned Order Releases TIME PHASED ORDER POINT GRID 3 PERIODS 4 5 6 Where: Order Qty - The planned order amount Order Lead Time - The number of periods between planned order release and receipt Forecast Demand = Expected customer demand Scheduled Receipts-Orders already placed with supplier (shipments on the way) Projected Available Inventory = Expected on hand inventory Planned Order Receipts = Planned quantity and arrival time of orders not yet placed Planned Order Releases Planned quantity and time of order placement 7 8 Example: Order Qty - 250 Order Lead Time - 3 Forecast Demand Scheduled Receipts Projected Available Inventory. 120 Planned Order Receipts Planned Order Releases 1 100 Order Qty = 250 Order Lead Time = 3 1 100 Forecast Demand Scheduled Receipts Projected Available Inventory. 120 Planned Order Receipts Planned Order Releases 250 2 100 250 20 2 100 250 Product A The key to TPOP planning is to keep projected available inventory from becoming negative (stock out) by planning order receipts to cover demand. In this instance, orders must be released three periods ahead of order receipt because lead time = 3. The completed order plan is shown below: 170 3 100 PERIODS 4 100 Product A 3 100 70 5 100 PERIODS 4 100 220 250 250 5 100 120 6 120 250 6 120 0 7 140 Period 3: Beginning Inventory [170] - Forecast Demand [100] = P.A. Inventory [70] Period 4: Beg. Inv. [70] - Forecast Demand [100] =-30 7 140 110 250 Period 1: Beginning Inventory [120] - Forecast Demand [100] = P.A. Inventory [20] Period 2: Beginning Inventory [20] - Forecast Demand [100] + Sch Receipts [250] - P.A. Inventory [170] Must plan order receipt for [250] and release 3 periods ahead (release period 1 to arrive period 4). P.A. Inventory (70-100+250)=220 8 160 8 160 200 250 Period 5: Beg. Inv. [220] - Forecast Demand [100] -120 Period 6: Beg. Inv. [120] - Forecast Demand [120]=0 P.A. Inventory = 0 No ordering necessary because P.A. inventory is not negative Period 7: Beg. Inv [0] - Forecast Demand [140]--140 Must plan order receipt for [250] and release 3 periods ahead (release period 4 to arrive period 7). P.A. Inventory-(0-140+250)-110 Period 8: Beg. Inv. [110]-forecast demand [160] --50 Must plan order receipt for [250] and release 3 periods ahead (release period 5 to arrive period 8). P.A. inventory=(110-160+250)-200 Projected available inventory beginning inventory+ any scheduled receipts + any planned order receipts - forecast demand. A planned order receipt must be used if projected available inventory would be negative without it. Order Qty = 150 Order Lead Time - 3 Application: Forecast Demand Scheduled Receipts Projected Available Inventory 140 Planned Order Receipts Planned Order Releases 150 1 100 Order Qty-Minimum Order Lead Time=4 Forecast Demand Scheduled Receipts Projected Available Inventory 0 Planned Order Receipts Planned Order Releases 40 1 100 100 0 2 100 150 110 90 150 2 120 120 0 3 90 120 0 Sometimes TPOP's are used in Lean Just in Time (JIT) systems. The minimum amount of inventory is ordered to avoid stockouts. 3 130 130 0 PERIODS 4 120 160 30 150 150 5 100 80 150 150 100 PERIODS 4 120 120 0 5 110 6 50 0 110 30 6 120 7 150 0 120 30 150 7 160 0 160 8 80 100 150 8 100 0 100 PART B Objectives: To demonstrate how Materials Requirement Planning (MRP) systems work and to show how Time Phased Order Point Grids are used in MRP. Information: An MRP system determines how much raw material to order and when it should be ordered. Many MRP systems plan to order the minimum quantity of materials necessary to meet the Master Production Schedule (MPS) and plan so that the materials will arrive Just In Time for production. For example, if the MPS calls for production of 100 Jeep Wranglers on December 1, then the MRP system would order 200 Jeep Wrangler front seats to arrive on December 1. An MRP system needs to following information: 1. A Master Production Schedule (how many Jeeps will be produced and when). 2. On hand inventory status of all raw materials. 3. A bill of materials (BOM) (a list of materials used to produce 1 Jeep Wrangler). Application: Given the following information: 1. Master Production Schedule - Produce 100 Jeep Wranglers in week 40 this year. 2. On-Hand Inventory Status: Part #/Quantity On-Hand B с D E F 30 (completed seats) 150 590 200 (with lug nuts in bags) 800 3. Jeep Wrangler Partial Bill Of Materials: Order Lead Time 3 weeks This partial BOM shows the relationship between the parts of the Jeep and the quantities necessary (in parentheses) to produce various components of the Jeep. For example, (2) front seats (B) and (5) tires (E) are required to build one Jeep (A). In addition, (5) adjustment buttons (C) and (4) bolts (D) are required to build one front seat (B). Plus, (5) lug nuts are required for each tire. Jeep B (2) Front Seat 00000 B: TTTT Determine how much of each material should be ordered to produce the 100 Jeeps that are released for production in week 40. Remember, some material is already on hand (See # 2). (Amount Needed-On-Hand Quantity) SHOW CALCULATIONS C: D: E: F: C (5) Front Seat Adjustment Buttons A Jeep Wrangler 00000 D (4) Front Seat Bolts E (5) Tire Planned Order Quantity (Units) F (5) Tire Lug Nuts This planning process is easier when TPOP grids are used. When planning with MRP, the TPOP grids are linked together vertically, with Master Production Schedule grid on top and the parts grids below. For example, the TPOP grids that follow represent the Jeep Wrangler (on top) and Part B (front seat) on bottom. Complete the Jeep Wrangler TPOP grid as you did earlier in the case to determine the planned order releases for the Jeep Wrangler. The planned order releases for the Wrangler is the Jeep Master Production Schedule. (The quantity of Jeeps starting production in each of these periods). Jeep Wrangler - Master Production Schedule Order Qty = 100 Order Lead Time = 2 Forecast Demand Scheduled Receipts Projected Available Inventory 420 Planned Order Receipts Planned Order Releases (Master Prod Schedule) 37 70 Part B (Front Seat) 37 Order Qty Minimum Order Lead Time-L Forecast Demand Scheduled Receipts Projected Available Inventory Planned Order Receipts Planned Order Releases 38 80 39 90 38 PERIODS 40 80 Part B demand depends entirely on the MPS for Jeeps. Using the Planned Order Releases, which reflect the Master Production Schedule (MPS), calculate the Part Demand for Part B (front seats) and place it in the Part B TPOP grid in the Forecast (Part) Demand row in the same time period as the Planned Order Releases (i.c., the MPS) for the full Jeep Wrangler product build. In addition, use the Bill of Material information on the previous page to find the lead time and beginning on-hand inventory for Part B. Lead time can be written in upper left hand portion of the grid. Projected available inventory can be written in the appropriate space on the grid, which is the space prior to period 1 (Week 37). Existing inventory carries forward until it is consumed by demand. Now complete the Part B grid to determine the planned order releases for Part B. 39 41 100 PERIODS 40 42 100 41 43 100 41 43 44 100 44 Managers are replacing the Reorder Point (ROP) Method with Time Phased Order Points (TPOP). Using TPOP's, managers are able to plan over several periods rather than period to period. Order Qty= Order Lead Time= Forecast Demand Scheduled Receipts Projected Available Inventory 120 Planned Order Receipts. Planned Order Releases TIME PHASED ORDER POINT GRID 3 PERIODS 4 5 6 Where: Order Qty - The planned order amount Order Lead Time - The number of periods between planned order release and receipt Forecast Demand = Expected customer demand Scheduled Receipts-Orders already placed with supplier (shipments on the way) Projected Available Inventory = Expected on hand inventory Planned Order Receipts = Planned quantity and arrival time of orders not yet placed Planned Order Releases Planned quantity and time of order placement 7 8 Example: Order Qty - 250 Order Lead Time - 3 Forecast Demand Scheduled Receipts Projected Available Inventory. 120 Planned Order Receipts Planned Order Releases 1 100 Order Qty = 250 Order Lead Time = 3 1 100 Forecast Demand Scheduled Receipts Projected Available Inventory. 120 Planned Order Receipts Planned Order Releases 250 2 100 250 20 2 100 250 Product A The key to TPOP planning is to keep projected available inventory from becoming negative (stock out) by planning order receipts to cover demand. In this instance, orders must be released three periods ahead of order receipt because lead time = 3. The completed order plan is shown below: 170 3 100 PERIODS 4 100 Product A 3 100 70 5 100 PERIODS 4 100 220 250 250 5 100 120 6 120 250 6 120 0 7 140 Period 3: Beginning Inventory [170] - Forecast Demand [100] = P.A. Inventory [70] Period 4: Beg. Inv. [70] - Forecast Demand [100] =-30 7 140 110 250 Period 1: Beginning Inventory [120] - Forecast Demand [100] = P.A. Inventory [20] Period 2: Beginning Inventory [20] - Forecast Demand [100] + Sch Receipts [250] - P.A. Inventory [170] Must plan order receipt for [250] and release 3 periods ahead (release period 1 to arrive period 4). P.A. Inventory (70-100+250)=220 8 160 8 160 200 250 Period 5: Beg. Inv. [220] - Forecast Demand [100] -120 Period 6: Beg. Inv. [120] - Forecast Demand [120]=0 P.A. Inventory = 0 No ordering necessary because P.A. inventory is not negative Period 7: Beg. Inv [0] - Forecast Demand [140]--140 Must plan order receipt for [250] and release 3 periods ahead (release period 4 to arrive period 7). P.A. Inventory-(0-140+250)-110 Period 8: Beg. Inv. [110]-forecast demand [160] --50 Must plan order receipt for [250] and release 3 periods ahead (release period 5 to arrive period 8). P.A. inventory=(110-160+250)-200 Projected available inventory beginning inventory+ any scheduled receipts + any planned order receipts - forecast demand. A planned order receipt must be used if projected available inventory would be negative without it. Order Qty = 150 Order Lead Time - 3 Application: Forecast Demand Scheduled Receipts Projected Available Inventory 140 Planned Order Receipts Planned Order Releases 150 1 100 Order Qty-Minimum Order Lead Time=4 Forecast Demand Scheduled Receipts Projected Available Inventory 0 Planned Order Receipts Planned Order Releases 40 1 100 100 0 2 100 150 110 90 150 2 120 120 0 3 90 120 0 Sometimes TPOP's are used in Lean Just in Time (JIT) systems. The minimum amount of inventory is ordered to avoid stockouts. 3 130 130 0 PERIODS 4 120 160 30 150 150 5 100 80 150 150 100 PERIODS 4 120 120 0 5 110 6 50 0 110 30 6 120 7 150 0 120 30 150 7 160 0 160 8 80 100 150 8 100 0 100 PART B Objectives: To demonstrate how Materials Requirement Planning (MRP) systems work and to show how Time Phased Order Point Grids are used in MRP. Information: An MRP system determines how much raw material to order and when it should be ordered. Many MRP systems plan to order the minimum quantity of materials necessary to meet the Master Production Schedule (MPS) and plan so that the materials will arrive Just In Time for production. For example, if the MPS calls for production of 100 Jeep Wranglers on December 1, then the MRP system would order 200 Jeep Wrangler front seats to arrive on December 1. An MRP system needs to following information: 1. A Master Production Schedule (how many Jeeps will be produced and when). 2. On hand inventory status of all raw materials. 3. A bill of materials (BOM) (a list of materials used to produce 1 Jeep Wrangler). Application: Given the following information: 1. Master Production Schedule - Produce 100 Jeep Wranglers in week 40 this year. 2. On-Hand Inventory Status: Part #/Quantity On-Hand B с D E F 30 (completed seats) 150 590 200 (with lug nuts in bags) 800 3. Jeep Wrangler Partial Bill Of Materials: Order Lead Time 3 weeks This partial BOM shows the relationship between the parts of the Jeep and the quantities necessary (in parentheses) to produce various components of the Jeep. For example, (2) front seats (B) and (5) tires (E) are required to build one Jeep (A). In addition, (5) adjustment buttons (C) and (4) bolts (D) are required to build one front seat (B). Plus, (5) lug nuts are required for each tire. Jeep B (2) Front Seat 00000 B: TTTT Determine how much of each material should be ordered to produce the 100 Jeeps that are released for production in week 40. Remember, some material is already on hand (See # 2). (Amount Needed-On-Hand Quantity) SHOW CALCULATIONS C: D: E: F: C (5) Front Seat Adjustment Buttons A Jeep Wrangler 00000 D (4) Front Seat Bolts E (5) Tire Planned Order Quantity (Units) F (5) Tire Lug Nuts This planning process is easier when TPOP grids are used. When planning with MRP, the TPOP grids are linked together vertically, with Master Production Schedule grid on top and the parts grids below. For example, the TPOP grids that follow represent the Jeep Wrangler (on top) and Part B (front seat) on bottom. Complete the Jeep Wrangler TPOP grid as you did earlier in the case to determine the planned order releases for the Jeep Wrangler. The planned order releases for the Wrangler is the Jeep Master Production Schedule. (The quantity of Jeeps starting production in each of these periods). Jeep Wrangler - Master Production Schedule Order Qty = 100 Order Lead Time = 2 Forecast Demand Scheduled Receipts Projected Available Inventory 420 Planned Order Receipts Planned Order Releases (Master Prod Schedule) 37 70 Part B (Front Seat) 37 Order Qty Minimum Order Lead Time-L Forecast Demand Scheduled Receipts Projected Available Inventory Planned Order Receipts Planned Order Releases 38 80 39 90 38 PERIODS 40 80 Part B demand depends entirely on the MPS for Jeeps. Using the Planned Order Releases, which reflect the Master Production Schedule (MPS), calculate the Part Demand for Part B (front seats) and place it in the Part B TPOP grid in the Forecast (Part) Demand row in the same time period as the Planned Order Releases (i.c., the MPS) for the full Jeep Wrangler product build. In addition, use the Bill of Material information on the previous page to find the lead time and beginning on-hand inventory for Part B. Lead time can be written in upper left hand portion of the grid. Projected available inventory can be written in the appropriate space on the grid, which is the space prior to period 1 (Week 37). Existing inventory carries forward until it is consumed by demand. Now complete the Part B grid to determine the planned order releases for Part B. 39 41 100 PERIODS 40 42 100 41 43 100 41 43 44 100 44
Expert Answer:
Answer rating: 100% (QA)
TimePhased Order Points TPOP is a method used by managers to plan inventory levels over several peri... View the full answer
Related Book For
An Introduction to Statistical Methods and Data Analysis
ISBN: 978-1305269477
7th edition
Authors: R. Lyman Ott, Micheal T. Longnecker
Posted Date:
Students also viewed these american history questions
-
Product Y is made from one component P, three components Q, and two compo- nents R. P is made from two part S, Q is made from one S, and R is made from two- part S and three part T. Other data...
-
The reorder point is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such...
-
How are the reorder point and lead time related in inventory analysis?
-
What were the reasons for the failure of the original purpose of FordDirect.com? Who eventually gained from the system and what were the gains?
-
A box contains 17 balls of which 10 are red and 7 are blue. A sample of 5 balls is chosen at random and placed in jar. Calculate the probability that: The jar contains exactly 3 red balls. The jar...
-
Bob built a website and gave the URL only to his n friends, which he numbered from 1 to n. He told friend number i that he/she can visit the website at most i times. Now Bob has a counter, C, keeping...
-
Management is considering three alternatives to satisfy an urgent need. Each of the alternatives will completely satisfy the need, so no combinations have to be considered. The first costs, operating...
-
The inventory of Wood4Fun and data on purchases and sales for a two-month period follow. The company closes its books at the end of each month. It uses the periodic inventory system. Required 1....
-
__________ are expenses that can be subtracted from total income in order to calculate tax liability. They may include child care expenses and union dues. deductions debentures tax credits dividends...
-
Understanding the relationship between business and society and the ways in which business and society are part of an interactive system.
-
Household purchases of durable goods $1293 Household purchases of nondurable goods $1717 Household purchases of services $301 All new residential building Purchases of capital equipment Domestic...
-
Jonathan would like to know if he is deemed to be carrying on a trade with his vinyl record sales, what will happen if the trade makes a loss in 2022/23, how will the loss be treated for tax purposes...
-
Gary, the production manager, was pleased at the company's income statement results. Actual DL cost was only $59,095, compared to the budgeted $69,000, while actual sales volume came in 200 units...
-
There are two positive numbers. Four times the small number plus3 times the big number is 32. Two times the small number plus thebig number is 12. What is 10 times the big number minus 6 times...
-
You notice your new client, Bob, has been using an improper method of accounting for many years. At your initial meeting, Bob informed you that the IRS has notified him that his two previous year tax...
-
3. Consider the circuit in Figure 1 with the following parameters: tsetup == 0.5, thold = 0.2, tpcq = 3, teeq = 2, td = 7, td = 5, td = 2, t = 3. pd (a) What is the minimum value for TCLK in the...
-
A company has budgeted the following purchases for the last four months of the current year. BUDGETED PURCHASES FOR LAST FOUR MONTHS OF CURRENT YEAR September $ 400,000 November $ October 450,000...
-
What is an insurable interest? Why is it important?
-
A supermarket chain staged a promotion for organic vegetables. The actual sales (Sales) of organic vegetables for the weekend of the promotion were obtained from scanner data at the checkout. Three...
-
Suppose that you are a regional director of an IRS office and that you are charged with sampling 1% of the returns with gross income levels above $ 15,000. How might you go about this? Would you use...
-
Refer to Exercise 14.23. a. Test for interactions and main effects. Use = .05. b. What can you conclude about the effects of pH and calcium on increases in mean trunk diameter for orange trees? In...
-
Explain the meaning of the term OD.
-
Who and how is OD meant to impact? Explain.
-
What is the systems perspective underlying OD? Explain.
Study smarter with the SolutionInn App