Question: Week 1 2 N 3 4 5 6 Task 1 30 80 100 0 Task 2 10 25 35 55 65 Task 3 10 20

 Week 1 2 N 3 4 5 6 Task 1 30
80 100 0 Task 2 10 25 35 55 65 Task 3

Week 1 2 N 3 4 5 6 Task 1 30 80 100 0 Task 2 10 25 35 55 65 Task 3 10 20 Task 4 Amounts are cumulative percent complete. 1.c.1. What is the cumulative earned value of the project at the end of week 6? (2 pts). 1.c.2. Is it good? (2 pts). 1.0.1. What is the CPI at the end of week 6? (2 pts). 1.0.1 What is the CV? (2 pts). 1.e. Calculate the FCAC using the first two methods described. (2 pts each)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!