Question: Week 1 2 N 3 4 5 6 Task 1 30 80 100 0 Task 2 10 25 35 55 65 Task 3 10 20

Week 1 2 N 3 4 5 6 Task 1 30 80 100 0 Task 2 10 25 35 55 65 Task 3 10 20 Task 4 Amounts are cumulative percent complete. 1.c.1. What is the cumulative earned value of the project at the end of week 6? (2 pts). 1.c.2. Is it good? (2 pts). 1.0.1. What is the CPI at the end of week 6? (2 pts). 1.0.1 What is the CV? (2 pts). 1.e. Calculate the FCAC using the first two methods described. (2 pts each)