Question: Week 3 Assignment Attached Files: File Week 3 template BCN 4 7 2 0 . xlsx ( 1 0 . 6 7 6 KB )

Week 3 Assignment
Attached Files:
File Week 3 template BCN4720.xlsx (10.676 KB)
Draw the logic node network schedule for the activities listed in the table and complete the Excel. Calculate the ES, EF, LS, LF, FF for each activity, and the overall project duration and mark the critical path.
Your completed assignment must include:
completed network diagram (hand drawn or use Excel)
overall duration of project
completed table showing ES, EF, LS, LF, FF, TF for each activity
critical path (critical activities) identified (you may highlight cells to denote critical activities if you use Excel)
Please submit your completed assignment as a MS Excel to the dropbox.
NOTE: Contact your Instructor if you have any questions about the assignment.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!