Question: Week 4 Gantt Chart Critical Path and Assignment Stadium Builders RS are preparing a bid to build a new 75,000 seat baseball stadium in Delaware.
Week 4 Gantt Chart Critical Path and Assignment
Stadium Builders RS are preparing a bid to build a new 75,000 seat baseball stadium in Delaware. The construction must start on June 1, 2021 and be completed in time for the 2024 season. A penalty clause of $90,000 per day of delay beyond April 20, 2024 is written into the contract.
Willie Robertson, the president of the company could net as much as $1.9MM on the project. He also said if they are successful, the prospects for future projects are very good since there is a projected interest in building new ball parks with modern luxury boxes.
Given the information provided below for the stadium project, answer the following questions:
- Will the project be completed by the April 20th deadline?
- How long will it take?
- What is the critical path for the project? (Highlight this on your Gantt chart if possible)
- Based on the schedule, would you recommend that the new owner pursue this construction contract? Why or Why not?
- Include a one page Gantt chart for the stadium schedule.
| ID | Activity | Duration | Predecessor(s) |
| 1 | Baseball Stadium |
|
|
| 2 | Get permits | 10 days | --- |
| 3 | Clear stadium site | 70 days | --- |
| 4 | Demolish building | 30 days | 3 |
| 5 | Set up construction site | 70 days | 4 |
| 6 | Drive support piling | 120 days | 3 |
| 7 | Pour lower concrete bowl | 120 days | 6 |
| 8 | Pour main concourse | 120 days | 4,7 |
| 9 | Install playing field | 90 days | 4,7 |
| 10 | Construct upper steel bowl | 120 days | 4,7 |
| 11 | Install seats | 140 days | 8, 10 |
| 12 | Build luxury boxes | 90 days | 8, 10 |
| 13 | Install Jumbotron | 30 days | 8, 10 |
| 14 | Stadium infrastructure | 120 days | 8, 10 |
| 15 | Construct steel canopy | 75 days | 11 |
| 16 | Light installation | 30 days | 15 |
| 17 | Build roof supports | 90 days | 7 |
| 18 | Construct roof | 180 days | 17 |
| 19 | Install roof tracks | 90 days | 17 |
| 20 21 | Install roof Inspection | 90 days 20days | 18, 19 9,12,14,16,20 |