Question: Week 6 - Critical Path Assignm... table [ [ Activity , Duration,Predecessors, ] , [ A , 3 days, - , ] , [

Week 6- Critical Path Assignm...
\table[[Activity,Duration,Predecessors,],[A,3 days,-,],[B,4 days,1,],[C,5 days,-,],[D,8 days,3,],[E,4 days,2,4,],[F,5 days,4,],[G,3 days,6,5,],[H,5 days,7,],[I,1 day,6,],[J,3 days,8,9,],[K,4 days,10,15],[L,2 days,,5],[Instructions:,10]]