Question: Week 7 Assignment: PERT, CPM, and Critical Path Diagram Define Critical path, Slack time, Resource Leveling and Dummy activity with reference to PERT and CPM.

 Week 7 Assignment: PERT, CPM, and Critical Path Diagram Define "Critical

Week 7 Assignment: PERT, CPM, and Critical Path Diagram Define "Critical path", "Slack time", "Resource Leveling" and "Dummy activity" with reference to PERT and CPM. An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!