Question: Week 9 Assignment - Crashing a Project Complete the worksheets below to calculate the total costs for each duration of the project. In each worksheet:

Week 9 Assignment - Crashing a Project
Complete the worksheets below to calculate the total costs for each duration of the project. In each worksheet:
- Fill in the values in all boxes, including the letter x where appropriate
- Respond everywhere you see an underscore (the cost questions and the question at the end)
- Highlight the box(es) for the activities that you crashed
- Add emphasis to arrows to show the critical path(s)(see example and note in the first worksheet below).
Project duration: 17 time units (indirect costs, \(\$ \mathbf{2200}\))
With the exception of the costs, I've completed this first worksheet for you. This worksheet shows the normal times, so I did not highlight any of the boxes.
Total direct cost for this duration:
Total project cost for this duration:
To add emphasis to the arrows on the critical path (as shown in the worksheet above):
1. Click on the arrow to select it (or use Ctrl+Click to select multiple arrows)
2. Click the Format tab on the ribbon
3. Click the Shape Outline dropdown arrow
4. Point to Weight, and click the \(\mathbf{3}\) pt option
5. Repeat for all arrows on the critical path(s).
Steps might vary slightly in different versions of Microsoft Word. Project duration: 16 time units (indirect costs, \$2000)
Total direct cost for this duration:
Total project cost for this duration:
Project duration: 15 time units (indirect costs, \(\$ \mathbf{1800}\)) Project duration: 14 time units (indirect costs, \$1650)
Total direct cost for this duration:
Total project cost for this duration:
Project duration: 13 time units (indirect costs, \(\$ \mathbf{1500}\))
Total direct cost for this duration:
Total project cost for this duration: Project duration: 12 time units (indirect costs, \$1450)
Total direct cost for this duration:
Total project cost for this duration:
Project duration: 11 time units (indirect costs, \$1400)
Total direct cost for this duration:
Total project cost for this duration:
No need to crash beyond this point. Just respond to the following question:
What is the optimum cost-time point for the project (i.e. the duration that produces the lowest overall cost)? Provide the number of time units and the total project costs for that time unit.
 Week 9 Assignment - Crashing a Project Complete the worksheets below

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!