Question: Week 9 Assignment - Crashing a Project please hand draw them so it is easier for me to see the answer Complete the worksheets below
Week Assignment Crashing a Project
please hand draw them so it is easier for me to see the answer
Complete the worksheets below to calculate the total costs for each duration of the project. In each worksheet:
Fill in the values in all boxes, including the letter x where appropriate
Respond everywhere you see an underscore the cost questions and the question at the end
Highlight the boxes for the activities that you crashed
Add emphasis to arrows to show the critical pathssee example and note in the first worksheet below
Project duration: time units indirect costs, $ mathbf
With the exception of the costs, I've completed this first worksheet for you. This worksheet shows the normal times, so I did not highlight any of the boxes.
Total direct cost for this duration:
Total project cost for this duration:
To add emphasis to the arrows on the critical path as shown in the worksheet above:
Click on the arrow to select it or use CtrlClick to select multiple arrows
Click the Format tab on the ribbon
Click the Shape Outline dropdown arrow
Point to Weight, and click the mathbf pt option
Repeat for all arrows on the critical paths
Steps might vary slightly in different versions of Microsoft Word. Project duration: time units indirect costs, $
Total direct cost for this duration:
Total project cost for this duration:
Project duration: time units indirect costs, $ mathbf Project duration: time units indirect costs, $
Total direct cost for this duration:
Total project cost for this duration:
Project duration: time units indirect costs, $ mathbf
Total direct cost for this duration:
Total project cost for this duration: Project duration: time units indirect costs, $
Total direct cost for this duration:
Total project cost for this duration:
Project duration: time units indirect costs, $
Total direct cost for this duration:
Total project cost for this duration:
No need to crash beyond this point. Just respond to the following question:
What is the optimum costtime point for the project ie the duration that produces the lowest overall cost Provide the number of time units and the total project costs for that time unit.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock