Question: week bag invent 1 2 3 4 5 6 7 8 gross requirements 100 0 100 200 100 200 200 100 schedule receipts 200 0

week bag invent 1 2 3 4 5 6 7 8
gross requirements 100 0 100 200 100 200 200 100
schedule receipts 200 0 0 0 0 0 0 0
projected on hand inventory 200
planned receipts
planned order releases

For the following MRP identify which week you have the second "planned order releases"(identify the week number the planned order is released and not when it is received, do not identify the quantity ordered)

Item:C Description: Pedestal Assembly Lot size: L4L

Lead time: 2 weeks

Safety stock:60