Question: Week TBC 1 2 3 4 5 Task 1 30 20 10 Task 2 50 10 30 10 Task 3 50 30 20 Task 4
|
| Week | |||||
|
| TBC | 1 | 2 | 3 | 4 | 5 |
| Task 1 | 30 | 20 | 10 |
|
|
|
| Task 2 | 50 |
| 10 | 30 | 10 |
|
| Task 3 | 50 |
|
| 30 | 20 |
|
| Task 4 | 20 |
|
|
| 10 | 10 |
BUDGETED COSTS
*Numbers are in $thousands
|
|
| Week | |||||
|
|
| 1 | 2 | 3 | 4 | 5 | |
| ACTUAL | Task 1 | 20 | 5 |
|
|
| |
| COSTS | Task 2 |
| 20 | 25 |
|
| |
|
| Task 3 |
|
| 35 |
|
| |
|
| Task 4 |
|
|
|
|
| |
*Numbers are in $thousands
|
| Week | |||||
|
|
| 1 | 2 | 3 | 4 | 5 |
| PERCENTAGE | Task 1 | 80 | 100 |
|
|
|
| OF WORK | Task 2 |
| 40 | 100 |
|
|
| COMPLETE | Task 3 |
|
| 70 |
|
|
|
| Task 4 |
|
|
|
|
|
a. What is the cumulative budgeted cost at the end of week 3? (2 pts)
b. What is the cumulative actual cost at the end of week 3? (2 pts)
c. What is the cumulative earned value at the end of week 3? (2 pts)
|
| Week | |||||
|
|
| 1 | 2 | 3 | 4 | 5 |
|
| Task 1 |
|
|
|
|
|
|
| Task 2 |
|
|
|
|
|
|
| Task 3 |
|
|
|
|
|
|
| Task 4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Total |
|
|
|
|
|
d. What is the Cost Performance Index at the end of week 3? (2 pts)
e. What is the Cost Variance at the end of week 3? (2 pts)
f. What is the Forecasted Cost at Completion? (Show both methods presented in the text) (2 pts)
g. What is the To-Complete Performance Index? (2 pts)
h. Provide a detailed analysis this projects status. Describe any required courses of action (3 pts)