Question: Week TBC 1 Task 1 30 10 Task 2 70 239 3 4 5 6 7 8 9 10 15 5 10 10 10

Week TBC 1 Task 1 30 10 Task 2 70 239 3

Week TBC 1 Task 1 30 10 Task 2 70 239 3 4 5 6 7 8 9 10 15 5 10 10 10 20 Task 3 40 25 10 10 5 25 Task 4 30 55 5 Total 170 10 25 15 10 25 15 35 10 5 20 22 20 a. What is the cumulative budget cost at the end of week 5? Show all work. b. Table below shows the actual costs for the above project. What is the cumulative actual cost at the end of week 5? Show all calculations.