Question: If the jobs displayed in Table 18.24 are processed using the earliestdue-date rule, what would be the lateness of job C? TABLE 18.24 Processing Times
If the jobs displayed in Table 18.24 are processed using the earliestdue-date rule, what would be the lateness of job C?

TABLE 18.24 Processing Times and Due Dates for Five Jobs Job C D E Processing time (weeks) Due date (weeks) 1 4 3 4 11 W LO CO