Question: Weighted Average Method, Physical Flow, Equivalent Units, Unit Costs, Cost Assignment, ABC Swasey Fabrication, Inc., manufactures frames for bicycles. Each frame passes through three processes:
Weighted Average Method, Physical Flow, Equivalent Units, Unit Costs, Cost Assignment, ABC
Swasey Fabrication, Inc., manufactures frames for bicycles. Each frame passes through three processes: Cutting, Welding, and Painting. In September, the Cutting Department of the Tulsa, Oklahoma, plant reported the following data:
- In Cutting, all direct materials are added at the beginning of the process.
- Beginning work in process consisted of 41,500 units, 20 percent complete with respect to direct labor and overhead. Costs in beginning inventory included direct materials, $1,205,000; direct labor, $222,800; and applied overhead, $150,000.
- Costs added to production during the month were direct materials, $2,698,400; direct labor, $3,454,700. Overhead was assigned using the following information:
Activity Rate Actual Driver Usage Inspection $150 per inspection hour 4,000 inspection hours Maintenance $750 per maintenance hour 1,600 maintenance hours Receiving $300 per receiving order 2,000 receiving orders - At the end of the month, 121,200 units were transferred out to Welding, leaving 13,400 units in ending work in process, or 25 percent complete.
Required:
1. Prepare a physical flow schedule.
| Units to account for: | |
| Units, beginning work in processUnits completed and transferred outUnits, ending work in processUnits, beginning work in process | Units, beginning work in process |
| Units completed and transferred outUnits, ending work in processUnits started (transferred in)Units started (transferred in) | Units started (transferred in) |
| Total units to account for | fill in the blank bf496ffb300404e_5 |
| Units accounted for: | |
| Units, beginning work in processUnits completed and transferred outUnits started (transferred in)Units completed and transferred out | Units completed and transferred out |
| Units, beginning work in processUnits, ending work in processUnits started (transferred in)Units, ending work in process | Units, ending work in process |
| Total units accounted for | fill in the blank bf496ffb300404e_10 |
Feedback
1. The physical flow schedule traces the units in process regardless of their stage of completion and provides the information needed for preparing the equivalent units schedule.
2. Calculate equivalent units of production for direct materials and conversion costs.
| Equivalent Units | |
| Direct Materials | fill in the blank 203ded09305fff3_1 |
| Conversion Costs | fill in the blank 203ded09305fff3_2 |
3. Compute unit cost under weighted average.
| Unit direct materials cost | $fill in the blank 203ded09305fff3_3 |
| Unit conversion costs | fill in the blank 203ded09305fff3_4 |
| Total unit cost | $fill in the blank 203ded09305fff3_5 |
DBC, TDABC, and ABC
The Bienestar Cardiology Clinic has two major activities: diagnostic and treatment. The two activities use four resources: nursing, medical technicians, cardiologists, and equipment. Detailed interviews have provided the following work distribution matrix shown below.
| Resources | ||||||
| Activity | Nursing | Technicians | Cardiologists | Equipment | Total Activity Time | |
| Diagnosing patients | 0.70 | 0.80 | 0.40 | 0.60 | 12,000 | hrs. |
| Treating patients | 0.30 | 0.20 | 0.60 | 0.40 | 8,000 | hrs. |
| Total time (hrs.) | 4,000 | 4,000 | 6,000 | 6,000 | 20,000 | |
| Cost | $80,000 | $80,000 | $320,000 | $320,000 | ||
The total time estimated corresponds to practical capacity (interviewers adjusted the total time to about 80 percent of the available time). The equipment time is measured in machine hours. Thus, the total time (at practical capacity) in the system is 20,000 hours. In considering the implementation of a TDABC model, the following unit times and transaction information are also provided:
| Unit Time | Driver | Expected Activity Driver Quantity | |||
| Diagnosing patients | 3 | hrs | No. of patients | 4,000 | |
| Treating patients | 0.8 | hr. | No. of treatments | 10,000 | |
The clinic has identified three types of patients: those with no heart disease, those with mild heart disease, and those with severe heart disease. The following additional data are provided:
| Patient Type | Diagnosing Patients | Treating Patients | Average Time Spent Servicing Each Patient Type (Cycle Time) |
| No disease | 2,000 | 0 | 3 hrs. |
| Mild disease | 1,500 | 5,000 | 5.6 hrs. |
| Severe disease | 500 | 5,000 | 11.0 hrs. |
| Activity cost | ? | ? |
Required:
1. Calculate the activity costs for diagnosing and treating patients. Using the activity costs calculated, calculate the unit cost of servicing each type of patient using traditional ABC.
| Activity rates | |
| Diagnosing | $fill in the blank 1 |
| Treating | $fill in the blank 2 |
Calculate the unit cost of servicing each type of patient using traditional ABC.
| Unit Cost | |
| No Disease | $fill in the blank 3 |
| Mild | $fill in the blank 4 |
| Severe | $fill in the blank 5 |
2. Using TDABC-derived activity rates, calculate the unit cost of servicing each type of patient. If required round your answer to two decimal places.
| Activity rates | |
| Diagnosing | $fill in the blank 6 |
| Treating | $fill in the blank 7 |
| Unit Cost | |
| No Disease | $fill in the blank 8 |
| Mild | $fill in the blank 9 |
| Severe | $fill in the blank 10 |
3. Using DBC, calculate the unit cost of servicing each type of patient. If required round your answer to two decimal places.
| Unit Cost | |
| No Disease | $fill in the blank 11 per patient |
| Mild | $fill in the blank 12 per patient |
| Severe | $fill in the blank 13 per patient |
4. Suppose that a medical consultant proposes a new patient-processing system that will shorten diagnostic and treatment times but would require more skilled nurses and technicians as well as an equipment upgrade. However, the total practical capacity would remain the same, at 20,000 hours. Total resource costs are predicted to increase by $100,000. The consultant estimates that the cycle times for each patient type would be reduced from 3 to 2 hours, 5.6 to 4.5 hours, and 11 to 9 hours. The physicians that own the clinic have expressed a willingness to implement the changes, provided that the unit cost of servicing each patient type decreases. Use DBC to estimate the new unit costs. If required round your answer to two decimal places.
| Unit Cost | |
| No Disease | $fill in the blank 14 per patient |
| Mild | $fill in the blank 15 per patient |
| Severe | $fill in the blank 16 per patient |
Should the clinic implement the new system?
YesNoYes
Direct Method, Reciprocal Method, Overhead Rates
Macalister Corporation is developing departmental overhead rates based on direct labor hours for its two production departmentsMolding and Assembly. The Molding Department employs 24 people, and the Assembly Department employs 78 people. Each person in these two departments works 2,200 hours per year. The production-related overhead costs for the Molding Department are budgeted at $155,000, and the Assembly Department costs are budgeted at $70,000. Two support departmentsEngineering and General Factorydirectly support the two production departments and have budgeted costs of $240,000 and $359,000, respectively. The production departments' overhead rates cannot be determined until the support departments' costs are properly allocated. The following schedule reflects the use of the Engineering Department's and General Factory Department's output by the various departments.
| Engineering | General Factory | Molding | Assembly | |
| Engineering hours | 2,000 | 2,300 | 7,700 | |
| Square feet | 136,080 | 434,160 | 77,760 |
For all requirements, round allocation ratios to four significant digits and round allocated costs to the nearest dollar.
Required:
1. Calculate the overhead rates per direct labor hour for the Molding Department and the Assembly Department using the direct allocation method to charge the production departments for support department costs. Round final answers to the nearest cent.
| Overhead rate per DLH | |
| Molding | $fill in the blank 1 |
| Assembly | $fill in the blank 2 |
2. Calculate the overhead rates per direct labor hour for the Molding Department and the Assembly Department using the reciprocal method to charge support department costs to each other and to the production departments. Round final answers to the nearest cent. Round your intermediate calculations to four decimal places.
| Overhead rate per DLH | |
| Molding | $fill in the blank 3 |
| Assembly | $fill in the blank 4 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
