Question: what am i doing wrong? The master budget at Monroe Manufacturing last period called for sales of 42,000 units at $42 each. The costs were
The master budget at Monroe Manufacturing last period called for sales of 42,000 units at $42 each. The costs were estimated to be $26 variable per unit and $524,000 fixed. During the period, actual production and actual sales were 45,000 units. The selling price was $41 per unit. Variable costs were $28 per unit. Actual fixed costs were $515,000. Required: Prepare a sales activity variance analysis. Note: Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts