Question: What are the Most Likely Duration (D) in task A and the Pessimistic Duration (PD) in task B given the following. State the formula and
What are the Most Likely Duration (D) in task A and the Pessimistic Duration (PD)
in task B given the following. State the formula and show all works.
TASK OD PD ED D
i) A 10 6 5 ?
ii) B 6 ? 6 8