Question: What are we doing when we create dependencies that effectively LEVEL our resources. For Example we schedule drywall crew to complete one area then move

What are we doing when we create dependencies that effectively LEVEL our resources.

For Example we schedule drywall crew to complete one area then move to the next even though both areas are ready for drywall at the same time but we only have one crew.

a)

Under utilizing out drywall crew.

b)

Creating dependencies to LEVEL a resource manually

c)

Use smart scheduling practices.

d)

Over Allocating the drywall crew.