Question: What best practice approach would one take to prioritize work when you dont have enough time to perform detailed work on every item? Top-down analysis

  1. What best practice approach would one take to prioritize work when you dont have enough time to perform detailed work on every item?
    1. Top-down analysis
    2. Bottom-up analysis
    3. Risk-based analysis
    4. Monte Carlo simulation analysis

  1. What tool would be excellent in analyzing whether you should repair your taxi or purchase a new taxi for your business?
    1. Fishbone diagram
    2. Monte Carlo simulation
    3. Delphi interviews
    4. Decision tree

  1. What is a good example of a task in stakeholder analysis?
    1. Documenting the boundaries of a stakeholders responsibilities
    2. Understanding the needs and expectations of advocates and opponents
    3. Deciding which stakeholder has the largest organization/most employees
    4. Communicating when the project is complete

  1. In this RACI diagram, which role is the primary person to execute the activity?

Director

Proj Mgr

Bus Analyst

Developer

Tech Supp

Customer

Activity 12

I

A

R

C

C

I

(Write answer here)

  1. A = Accountable
  2. C = Consulted
  3. I = Informed
  4. R = Responsible

  1. There can be more than one person Accountable for a task in RACI? (True or False)
  1. True
  2. False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!