Question: What can you conclude by looking at the combined earned value data for the project?May June July Aug Sep Oct Software Customization Monthly Plan Monthly

What can you conclude by looking at the combined earned value data for the project?May June July Aug Sep Oct
Software Customization Monthly Plan
Monthly Status Plan BCWS $120,000 $192,000 $192,000 $192,000 $192,000 $60,000
Actual Burn ACWP $119,000 $187,000 $165,000 $189,000 $186,000 $0
Actual Perform BCWP $133,250 $197,000 $220,000 $215,000 $240,000 $0
Rolling Status Plan BCWS
Actual Burn ACWP
Actual Perform BCWP
Rolling Ratios Schedule Impact SV = BCWP BCWS $13,250 $5,000 $28,000 $23,000 $48,000
SPI = BCWP / BCWS 111.04%102.60%114.58%111.98%125.00%
Cost Impact CV = BCWP ACWP $14,250 $10,000 $55,000 $26,000 $54,000 $0
CPI = BCWP / ACWP 111.97%105.35%133.33%113.76%129.03%
Control Ratio CR = SPI \times CPI 1.241.081.531.271.61
Technical Infrastructure
Monthly Status Plan BCWS $120,000 $192,000 $192,000 $192,000 $192,000
Actual Burn ACWP $120,000 $215,000 $192,000 $216,500 $170,000 $0
Actual Perform BCWP $120,000 $170,000 $173,000 $190,000 $185,000 $0
Rolling Status Plan BCWS
Actual Burn ACWP
Actual Perform BCWP
Rolling Ratios Schedule Impact SV = BCWP BCWS $0-$22,000-$19,000-$2,000-$7,000
SPI = BCWP / BCWS 100.00%88.54%90.10%98.96%96.35%
Cost Impact CV = BCWP ACWP $0-$45,000-$19,000-$26,500 $15,000 $0
CPI = BCWP / ACWP 100.00%79.07%90.10%87.76%108.82%
Control Ratio CR = SPI \times CPI 1.000.700.810.871.050.00
Combined Projects
Monthly Status Plan BCWS $240,000 $384,000 $384,000 $384,000 $384,000
Actual Burn ACWP $239,000 $402,000 $357,000 $405,500 $356,000 $0
Actual Perform BCWP $253,250 $367,000 $393,000 $405,000 $425,000 $0
Rolling Status Plan BCWS
Actual Burn ACWP
Actual Perform BCWP
Rolling Ratios Schedule Impact SV = BCWP BCWS $13,250-$17,000 $9,000 $21,000 $41,000 $0
SPI = BCWP / BCWS 105.52%95.57%102.34%105.47%110.68%
Cost Impact CV = BCWP ACWP $14,250-$35,000 $36,000-$500 $69,000 $0
CPI = BCWP / ACWP 105.96%91.29%110.08%99.88%119.38%
Control Ratio CR = SPI \times CPI 1.120.871.131.051.320.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!