What cost estimating technique would be indicated for the following situation?The program is later in the EMD phase and is going to have a MS C Decision in about a year.The esitmate is due several months to a year from now.The estimate needs to be very accurate and objective.Detailed labor and material are available.The design effort has completed the Work Breakdown Structure definition and the sum of the costs determines the total system cost.