Question: What does a change - control process consist of ? Group of answer choices a . Clearly delineated procedures for approval of a change and
What does a changecontrol process consist of
Group of answer choices
a Clearly delineated procedures for approval of a change and corresponding documentation.
b A meeting where the client may make changes to the project plan.
c A clients verbal request to make a change in the project plan.
d A clearly delineated procedure where the project team can add changes to the project.