Question: What does it mean if the Earned Value is equal to Actual Cost? Question 8 Select one: a . Project is on budget and on
What does it mean if the Earned Value is equal to Actual Cost?
Question Select one:
a
Project is on budget and on schedule
b
There is no schedule variance
c
There is no cost variance
d
Schedule Variance Index is