Question: What does the precedent chart below tell us about this assembly process: TASK PRECEDING TASK A - B - C A , B D C
What does the precedent chart below tell us about this assembly process:
TASK PRECEDING TASK
A
B
C A B
D C
E D
F DE
tasks A and B are the bottlenecks
task D happens three times in the work station
task F cannot be completed until after task D and E are complete
tasks A and B require the least amount of time to complete