Question: What does the term critical path refer to in project scheduling?The tasks that can be completed in parallelThe longest sequence of tasks to complete a

What does the term "critical path" refer to in project scheduling?The tasks that can be completed in parallelThe longest sequence of tasks to complete a projectThe activities with the least resource allocationThe least expensive tasks